Update the Work Order meter

Before you begin

Requires the Edit Meter permission — see Work Order permissions. The Work Order must be open; Fleet360 doesn't offer the meter edit control on a closed Work Order.

Steps

  1. Open the Work Order and find the WO Meter field in the Work Order summary.

  2. Select the pencil (edit) icon next to the WO Meter value.

    The meter update drawer opens, showing the asset's current reading.

  3. Enter the new reading in the meter field, labeled with the asset's meter type (for example, Miles or Hours). If your organization prompts for alternate meters, also enter the new reading in the Alternate Meter field(s) shown.

  4. Select Save.

    The drawer closes and the WO Meter value on the Work Order updates to the reading you entered.

If this step fails

If the reading you enter is higher than the maximum allowed jump for this meter, Fleet360 blocks the save with an error. A user with meter-override authorization can approve the change from an on-screen authorization prompt; otherwise, enter a reading within the allowed range and select Save again.

See also